Tuesday, July 29, 2008

Columns


REBAR
Originally uploaded by rob1171
Columns on the West side of the Parking Garage.
Its nice to see something going vertical. Also, notice the foam insulation on the left side of the picture. The insulation was required to get the building to meet the new energy codes. This makes absolutely no sense to me as the building is in Las Vegas and the entire South East corner of the underground parking garage is open......

Go figure.

Tuesday, July 22, 2008

Parking Garage Footings


072208
Originally uploaded by rob1171
Footings Inspection Passed. Pour will begin 7/23/08 2:00 am

Tuesday, July 15, 2008

Footing Pad - Ready for rebar


photo.jpg
Originally uploaded by rob1171
This is on the south end of the property, where the entrance to the UG Parking Garage will be.

10lbs of @#$% in a 5lb Bag


Power telphone what else
Originally uploaded by rob1171
None of these Underground Utilities are supposed to be here.

This is what happens when you develop a parcel that has everything built our around it.

Footing Rebar


photo.jpg
Originally uploaded by rob1171
Finally!
Rebar has begun along the North Wall.

Monday, July 14, 2008

Rob


Rob
Originally uploaded by rob1171
Hard at work.......Kinda

A big hole


photo.jpg
Originally uploaded by rob1171
Notice the planes landing/taking off in the background

Footing Excavation


photo.jpg
Originally uploaded by rob1171
Matt inspecting the footings. Footings were doubled to eliminate the need for footing drains.

Footing Excavation


photo.jpg
Originally uploaded by rob1171
Caliche, such wonderfully expensive stuff!

Footing Excavation


Footing Excavation
Originally uploaded by rob1171
The task of footing excavation has been a challenge as we have hit more Caliche. The footing size also doubled as we needed to eliminate the footing drains to to non access behind the shoring.

Footing Excavation


Footing Excavation
Originally uploaded by rob1171

Tuesday, July 8, 2008

Escondido - The Start

This project is on the corner of Sunset Rd & Escondido in Las Vegas, NV right across from McCarran Aiport.

We are constructing a (2) Storey Building (11,500 sq/ft footprint) with an underground parking garage of 24,000 sq/ft.

This property has gone through (2) zoning changes and a special use permit and has taken almost (2) years from conception to ground breaking.

It has been a struggle but now the fun begins.